Kronthal School

Kronberg, 2010
Schools/educational facilities
Architecture: Dörr Ludolf Wimmer Architekten, Berlin

schneider+schumacher Bau- und Projektmanagement GmbH took over the phase of the construction supervision for Kronthal School in Kronberg. The 12 million € project was realised within a construction period of 18 months. Berlin architect, Ludolf Dorr Wimmer designed the complex (www.doerr-Ludolf-wimmer.de).

Involved s+s unitsB

Technical details:

Procurement documentation: Public
Service phases (HOAI): 7,8
Client: Kreisausschuss des Hochtaunuskreises
Construction management: schneider+schumacher Bau- und Projektmanagement GmbH
Lead construction manager: Maximilian Büschl
Gross floor area: 7,382 m²